August
Current Status and Funding Limitations
The construction phase of the project currently has a budget of $3 million, funded equally by the City and County with $1.5 million each. Scorpio’s recent budget estimate, based on 50% completed construction documents, is $2,931,192. This estimate covers key improvements including site drainage, structural repairs to the building and preservation efforts.
Major structural work includes replacing the auditorium’s roof and roof trusses, masonry repairs, and foundation stabilization using helical piles on the south wing. A significant focus is on preserving the building’s historic windows, which will be carefully removed, abated, restored, refinished and reinstalled.
Key budget allocations include:
- 70% for stabilizing the auditorium, including the new roof and roof trusses
- 25% for work on the service wing addition
- 5% for site drainage improvements
Please note:
- The current construction budget fully utilizes the Phase I structural stabilization funds.
- This budget covers only essential structural repairs and does not include upgrades necessary to reopen the building for public use.
Additional work required to reopen the facility includes:
- Mechanical system upgrades and replacements
- Installation of new flooring and lighting
- Code-compliant modifications
The combined estimated cost for Phase I (structural repairs) and Phase II (interior and systems upgrades) is $6,645,690.
To support final cost estimates for the Phase I design, the City recently completed microbial testing—used to detect and quantify potential biological contaminants—and conducted ground-penetrating radar (GPR) analysis to determine whether structural reinforcements were previously added to the auditorium’s exterior walls. Final pricing for structural repairs, along with a preliminary estimate for the full scope of work required to reopen the facility, is anticipated by the end of the year.
Projected Timeline
Design and permitting for the Phase 1 structural repairs are expected to be completed by the end of 2025. Construction could begin in early 2026 and is anticipated to take approximately 12 months. It is important to note that the current project budget covers only Phase 1, which includes structural stabilization. As such, the building will not be operational or have power restored upon completion of this phase.
March–May
Design progresses from 50% to 100% Construction Documents (CDs).