July 31
This dedicated webpage has been developed to serve as a central hub for information, including materials from past meetings, ongoing project updates and details about upcoming events and future developments. It will be updated regularly to ensure timely and consistent communication with the public.
Current Status and Funding Limitations
The current budget for the construction phase of the project is $3 million, comprised of $1.5 million from City funds and $1.5 million in County funding. Scorpio submitted a budget estimate based on the 50% CDs of $2,931,192. The estimate includes site drainage improvements and building structural improvements, including replacing the auditorium roof structure, masonry repairs and reinforcement, and helical piles (foundation stabilization) at the south wing. The existing windows have been identified as the mostcritical item to preserve. They will be removed, abated, restored, refinished and reinstalled to best preserve them. Approximately 70% of the cost is to stabilize the auditorium, including the installation of a new roof and roof trusses. Work at the service wing addition is approximately 25% of the cost, and the site drainage improvements are about 5% of the cost.
Please note the current construction estimate depletes the Phase I structural stabilization funding allocation, only includes structural repairs and would not reopen the building for programming.
To reopen the building, additional improvements beyond the Phase 1 structural stabilization will be required. These include upgrades and replacements to mechanical systems, installation of new flooring, new lights and code-required modifications. The combined cost of Phase 1 structural repairs and Phase 2 interior and systems upgrades is estimated to exceed $6 million. Currently, the City is conducting microbial testing and x-ray analysis to inform the final design and cost estimates for Phase 1. Final pricing for the structural repairs, along with a preliminary estimate for the full scope of work needed to reopen the facility, is expected by the end of the calendar year following the completion of testing.
Projected Timeline
Design and permitting for the Phase 1 structural repairs are expected to be completed by the end of 2025. Construction could begin in early 2026 and is anticipated to take approximately 12 months. It is important to note that the current project budget covers only Phase 1, which includes structural stabilization. As such, the building will not be operational or have power restored upon completion of this phase.
March–May
Design progresses from 50% to 100% Construction Documents (CDs).